Foundation Poured

The foundation forms were set and the walls promptly poured last week. The foundation contractor did an excellent job pouring a level, square, foundation which exactly matches the plan dimensions. This alone should make setting the SIPS much easier.

However, there were a couple of issues with the way the hole was excavated, resulting in the first unplanned change on the project-stepping the foundation walls. As a result of the stepped foundation wall, a window slated for the bedroom now longer fits. Unfortunately, after exploring options, it looks like there is no feasible way to modify the foundation and fit the window.

IMG_3472

IMG_3490

The fall foliage was beautiful and I couldn’t resist taking a couple photos of the view.

IMG_3483

The structural engineer called for a hefty footing under a post which splits the span of my ridge beam. The contractor poured a 12inch x 5 foot x 5 foot footer under the post location.

IMG_3478

The plumber laid pipes for the kitchen sink, bathroom, and washing machine.

IMG_3479